NTFPD Fire Station 53 | Seismic Evaluation Engineering

As part of determining the feasibility of remodeling the station to meet future needs versus constructing a new station, North Tahoe Fire Protection District retained Linchpin Senior Principal Doug Gadow to perform a seismic evaluation of the existing building. Mr. Gadow developed a list of issues and recommended mitigation measures for the District’s use.

Slide NTFPD Fire Station 53-1 Slide NTFPD Fire Station 53-2

Linchpin Structural Engineering, Inc. | Seismic Evaluation Engineering

Mr Gadow, was Engineer of Record for this project at his previous employer, Gary Davis Group.